Sewer District #1

Completed

  • December 2023 – Plans delivered to NYSDOT
  • January 2024 – NYSDEC submission
  • July 2024 – Inter-Municipal agreement (IMA) with Brownville
  • July 2024 – WIIA Grant submitted
  • August 2024 – EDA Grant application
  • July-November 2024 – NYSDEC and NYSDOT approval
  • December 2024 – Additional comments received from NYSDEC
    • B&L providing responses
    • Scheduling meeting with Brownville for NYSDEC requested acceptance letter

Next Steps

  • Ongoing – Easement coordination
    • January 2024 – Meeting with remaining property owners
    • County easements expected within the next month
  • Winter 2024 – Bidding
  • Spring-Summer 2025 – Construction

 

*****Once complete, this infrastructure will serve the Watertown International Airport only*****