Sewer District #1
Completed
- December 2023 – Plans delivered to NYSDOT
- January 2024 – NYSDEC submission
- July 2024 – Inter-Municipal agreement (IMA) with Brownville
- July 2024 – WIIA Grant submitted
- August 2024 – EDA Grant application
- July-November 2024 – NYSDEC and NYSDOT approval
- December 2024 – Additional comments received from NYSDEC
- B&L providing responses
- Scheduling meeting with Brownville for NYSDEC requested acceptance letter
Next Steps
- Ongoing – Easement coordination
- January 2024 – Meeting with remaining property owners
- County easements expected within the next month
- Winter 2024 – Bidding
- Spring-Summer 2025 – Construction
*****Once complete, this infrastructure will serve the Watertown International Airport only*****