Water Service Area # 8

Completed

  • April 2023 – Board approve report and scheduled public hearing
  • May 2023 – Public hearing and pass resolution forming and re-confirming Water District #8
  • June 2023 – Re-list project on 2024 DWSRF IUP listing
  • August 2023 – Submit WIIA Grant application
  • October 2023 – NYS Comptroller application completed
  • December 2023 – Project awarded $5 million WIIA Grant
  • July-August 2024 – Surveyor field work

Next Steps

  • TBD – Comptroller’s approval
    • awaiting correspondence from Comptroller’s Office
  • Bond resolution, Estoppel notice, Final order (after Comptroller approval)