Water system improvements
Contract #3 – Old Rome State Road water main
- January-June 2024 – Design plans and specs
- September 2024 – Submit to Jefferson County
- December 2024-January 2025 – Agency approval
- Received comments from NYSDOH (11/5/24)
- B&L addressing and providing response
- Spring 2025 – Bidding
- Spring-Summer 2025 – Construction
Water meter replacements
- January 2024 – Core & Main contract award
- March-June 2024 – Antenna installation
- Ongoing – Meter replacements by Town staff
- Ongoing – Billing integration
- Core & Main to schedule training session